Bilaspur-Jabalpur Highway Still Unfinished After Three Years, Congress Blames Contractor and PWD

A damaged, potholed stretch of a rural national highway in central India
Photo: AI-generated illustration

The Marwahi stretch of the Bilaspur-Jabalpur national highway in Chhattisgarh’s Gaurela-Pendra-Marwahi (GPM) district has stayed unfinished for three years, Patrika reported. The roughly 100-km trip from the district to Bilaspur now takes more than four hours, and Congress state president Deepak Baij blames contractor and departmental failures for the delay.

Patrika reported that the Marwahi section, about 80 km long, has frequent jams and broken patches that have slowed traffic for years. Residents and commuters say the poor surface has made the district harder to reach from the rest of the state, a complaint Baij repeated this week.

The district sits in the hill and forest belt of northern Chhattisgarh, and the highway is its main link to Bilaspur, the nearest large city with hospitals, courts and government offices that GPM residents routinely travel to.

A district that is itself fairly new

Gaurela-Pendra-Marwahi became Chhattisgarh’s 28th district in February 2020, carved out of Bilaspur district under the Congress government that Baghel then led. That history is part of why the unfinished highway has become a political flashpoint: the district’s own creation was meant to bring it closer administrative attention, and critics argue a core connectivity project has instead stalled for three years running.

Before the 2020 reorganisation, Gaurela, Pendra and Marwahi were tehsils within Bilaspur district. The highway link to Bilaspur predates the district split and has long served as the area’s main route to the plains, which is why its condition affects nearly every resident who needs to leave the district for a hospital, a court, or a government office.

What Baij said about the delay

Patrika reported that Deepak Baij, president of the Chhattisgarh Congress, said poor roads have effectively cut off GPM district from the rest of the state. “Bad roads have turned this district into an island,” he said, in a comment translated from Hindi.

Baij said the state government has been unable to even keep up with repairs on the stretch, let alone build new roads, according to Patrika. He placed responsibility on both the contractor handling the work and the state’s public works department.

The Rs 16,000 crore dispute

Patrika reported that former chief minister Bhupesh Baghel widened the criticism to the state’s road-building record as a whole. Baghel said the current government has stopped road works worth Rs 16,000 crore that were approved under the previous Congress administration he led.

Baghel directed his criticism at PWD minister Arun Sao’s handling of the department’s road projects, according to the report. Patrika’s report did not include a response from Sao or the state public works department to either Baghel’s or Baij’s claims.

A contractor already flagged once

This is not the first time the Marwahi stretch has drawn official attention. Patrika reported that Bilaspur MP and Union minister of state Tokhan Sahu had earlier called for the contractor on the project to be blacklisted and for fresh tenders to be issued.

Patrika’s report found no sign that Sahu’s intervention changed anything on the ground. The contractor was not named in the report, and no blacklisting or retendering has been confirmed.

What it means for commuters

For residents of GPM district, the practical effect is a trip that should take a fraction of the time it does. Patrika reported that the roughly 100-km run to Bilaspur, ordinarily a two-hour drive on a functioning national highway, now regularly takes more than four hours because of the unfinished sections and resulting congestion.

That gap matters for people traveling to Bilaspur for hospital visits, court dates or government work, and it is the practical complaint underlying Baij’s “island” remark.

The dispute over the highway has also become entangled with the broader Rs 16,000 crore political argument between Baghel and the current government over which road projects have been funded and which have stalled, a dispute that is likely to continue as both sides cite the Marwahi stretch as evidence for their case.

Neither the state PWD nor Sao’s office has publicly responded to the latest round of criticism, and no revised completion date for the Marwahi stretch has been announced.

Frequently asked questions

Which highway is affected? The Bilaspur-Jabalpur national highway’s Marwahi stretch, about 80 km long, inside Chhattisgarh’s Gaurela-Pendra-Marwahi district.

How long has it been unfinished? Patrika reported the stretch has remained incomplete for three years.

Who is blamed for the delay? Congress leaders Deepak Baij and Bhupesh Baghel point to the contractor and the state public works department, headed by minister Arun Sao. The contractor has not been named, and the PWD has not publicly responded.

Has anyone tried to act on this before? Bilaspur MP Tokhan Sahu earlier called for the contractor to be blacklisted and for new tenders to be floated, according to Patrika, though no retendering has been confirmed.

Source: Patrika.