The U.S. Department of War’s Office of Strategic Capital has given materials company 6K a conditional commitment for a loan of up to $250 million. The money is meant to support domestic production of cathode materials used in lithium-ion batteries at a planned facility in Jackson, Tennessee, 6K said on November 5.
What the loan covers
6K says the funds are meant to support construction of its PlusCAM production facility in Jackson, Tennessee, which makes nickel-manganese-cobalt (NMC) cathode active material, a key component inside lithium-ion batteries. The company said the project is expected to create more than 200 high-quality jobs.
6K CEO Saurabh Ullal said the commitment would help the company build out secure, domestically made cathode supply. The Jackson plant is not a new project for 6K: the company’s PlusCAM facility had already received a separate $50 million grant from the Department of Energy’s Office of Manufacturing and Energy Supply Chains, under an agreement executed in December 2023, toward a project the company put at more than $200 million in total cost.
At the time of that 2023 award, trade outlet UCBJournal reported the Jackson facility was expected to create around 230 new jobs in Madison County, a figure close to the “more than 200” jobs 6K now cites for the War Department-backed phase of the project.
Why the Pentagon is backing a battery materials company
In its press release, 6K said the United States remains heavily dependent on cathode materials produced by what it called “Foreign Entities of Concern,” without naming a specific country.
The Office of Strategic Capital was created by the FY2024 National Defense Authorization Act, signed into law in December 2023, and sits inside the Office of the Secretary of Defense under 10 U.S.C. Section 149, according to a Congressional Research Service report. Its mandate is to use loans and loan guarantees to pull private capital into technologies Congress has flagged as critical to national security, with its new-loan authority currently set to expire in October 2028.
The 6K loan follows a similar pattern elsewhere in the battery materials industry this year. Multiple outlets, including Dealroom and Law4Startups, reported that the Department of War’s Office of Strategic Capital committed up to $1.4 billion in August 2026 to battery materials company Sila to scale up domestic silicon-carbon anode production, a parallel effort on the anode side of the same supply chain.
The commitment also lands in the middle of a wider federal push on defense-linked supply chains. Law firm Greenberg Traurig’s policy tracker notes that President Trump signed an executive order in July 2026 on securing America’s defense supply chains, directing defense contractors to map and prioritize domestic and allied sourcing of critical materials, a category that includes battery inputs like cathode and anode material.
Who is 6K
6K describes itself as an advanced materials company roughly 12 years old, based in North Andover, Massachusetts, with the battery materials work organized under its 6K Energy division and a separate 6K Additive division that makes metal powders. 6K Additive previously won a five-year blanket purchase agreement with the US Army’s Development Command for its powders, a separate line of federal business from the Jackson, Tennessee cathode project.
What still has to happen before the money moves
6K’s press release is explicit that this is a conditional commitment, not a disbursed loan. The company said the funds depend on authorizations from government authorities, continued availability of congressional appropriations, and due diligence to the Department of War’s satisfaction, along with standard financial, legal, technical and regulatory conditions.
6K’s release did not give a construction completion date or a production capacity figure for the Jackson plant. The pace at which the Office of Strategic Capital moves from a conditional commitment to a signed loan agreement, as it did earlier this year with Sila, will be the next concrete signal of whether the Jackson project is on track.
FAQ
What is cathode active material, and why does it matter?
It is the material inside a lithium-ion battery’s positive electrode that largely determines the battery’s energy storage capacity. 6K’s PlusCAM facility will produce the nickel-manganese-cobalt (NMC) version used in batteries for defense platforms as well as civilian applications.
Is the $250 million guaranteed?
No. 6K describes it as a conditional commitment that still needs government authorizations, appropriations funding and due diligence before any money is disbursed.
Who is 6K?
6K is a Massachusetts-based advanced materials company led by CEO Saurabh Ullal that has previously received other federal support, including an earlier Department of Energy grant and an Army blanket purchase agreement for its metal powders business, for its battery materials manufacturing plans.
What happens to the Sila loan this compares to?
Sila’s $1.4 billion commitment from the Office of Strategic Capital, reported in August 2026, targets silicon-carbon battery anode material rather than cathode material, making it a parallel bet on a different part of the same battery supply chain rather than a direct comparison in scale.
What happens next depends on whether 6K clears the Department of War’s due diligence and appropriations conditions, and whether the company then sets a firm construction timeline for the Jackson plant.