PWD Cuts Through Balod Hill to Connect Junwani and Chikhli Villages With New Road

Last updated: October 27, 2026, 02:30 PM IST.

The Public Works Department has started cutting through a hill in Balod district’s Dondi Lohara assembly constituency to build a direct road between Junwani and Chikhli villages. The state government has sanctioned Rs 12 crore for the project, approved by Chief Minister Vishnu Deo Sai, PWD Executive Engineer R.N. Usendi told Patrika.

Junwani and Chikhli are separated by a forested ridge in the hilly belt of Dondi Lohara. Residents currently rely on a detour of 25 to 30 kilometres, or on risky forest paths, to travel between the two villages, according to PWD figures cited by Patrika. The new alignment is expected to cut that distance to roughly 4 to 5 kilometres once the road is finished.

Former janpad panchayat member Sanjay Bais said residents have been asking for a direct road between the two villages for close to 40 years. Villagers Ramsay Mandavi, 62, and farmer Santosh Kumar told Patrika that the long detour has made it harder to move patients, traders, and farm produce between the villages.

Both Junwani and Chikhli fall within Dondi Lohara, one of Balod district’s assembly constituencies. The hill separating the two villages has, until now, meant the shorter straight-line distance between them counted for little, since the only usable routes ran around the ridge or through the forest, according to Patrika’s reporting.

A Demand Nearly Four Decades Old

Bais’s account places the origin of the demand at roughly four decades ago, well before most of the district’s current road network existed. The hill between Junwani and Chikhli left both villages cut off from each other despite their proximity, forcing residents onto the longer detour or forest tracks for every trip.

That gap is now closing with sanctioned funds and PWD crews actively cutting into the hillside, according to Patrika’s on-ground reporting from Balod. Patrika’s report did not specify the exact date the hill-cutting work began, only that it is already under way.

What the Construction Work Involves

PWD Executive Engineer R.N. Usendi said the project covers hill cutting, retaining walls, culverts, bridges, drainage work, and asphalt surfacing. The department is carrying out the work in line with forest and environment department rules, given that the alignment cuts through hill and forest terrain, Usendi told Patrika.

The combination of retaining walls and drainage structures is meant to stabilise the cut hillside through the monsoon, alongside the culverts and bridges needed to carry the road across the terrain between the two villages. Usendi described the scope to Patrika but did not give a breakdown of how much of each component, hill cutting, retaining walls, culverts, bridges, drainage, or the final asphalt layer, has been completed so far.

Funding and the One-Year Timeline

The Chhattisgarh government has sanctioned Rs 12 crore for the Junwani-Chikhli road, with Chief Minister Vishnu Deo Sai approving the funds, Patrika reported. The PWD is aiming to complete the project within one year of the start of construction.

Usendi did not give Patrika a specific start date for the hill-cutting work beyond confirming it is already under way, and the one-year target covers the full scope of the project, from cutting the hill to the final asphalt surface. Whether that timeline holds will depend partly on how the retaining wall and drainage work, both monsoon-sensitive, proceed once the hill cutting itself is finished.

What Changes Once the Road Opens

Once finished, the road is expected to shorten the journey between Junwani and Chikhli from a 25 to 30 kilometre detour, or a risky forest path, to about 4 to 5 kilometres, based on PWD’s own figures reported by Patrika.

Ramsay Mandavi and Santosh Kumar told Patrika that the shorter route matters most for getting patients to care quickly, for traders moving goods between the villages, and for farmers transporting produce, all of which the long detour has made slower and harder.

Until the new alignment opens, residents moving between Junwani and Chikhli still face the same choice they have had for years, the 25 to 30 kilometre detour or the forest path, Patrika’s report indicated. The PWD figures suggest that choice changes once the shorter 4 to 5 kilometre stretch is usable.

Frequently Asked Questions

How much shorter will the new road make the journey between Junwani and Chikhli?
Based on PWD figures reported by Patrika, the route should shrink to roughly 4 to 5 kilometres, down from the current 25 to 30 kilometre detour or forest path.

When is the project expected to be completed?
PWD Executive Engineer R.N. Usendi told Patrika the department is aiming to finish within one year of the start of construction, covering everything from the hill cutting to the final asphalt surface.

Who approved the funding for the road?
The Chhattisgarh government sanctioned Rs 12 crore for the project, with Chief Minister Vishnu Deo Sai approving the funds, according to Patrika.

With PWD crews already cutting into the hillside, the next marker to watch is whether the one-year completion target holds once the monsoon-sensitive retaining wall and drainage work gets under way.

Source: Patrika (Balod).